二○○三年浙江省建設工程概預算編審人員資格考試.doc
進入下載頁
二○○三年浙江省建設工程概預算編審人員資格考試
《建筑工程預算》模擬試卷(開卷)
一、判斷題:(每小題1分,共10分。正確的在括號內打“√”,錯誤的打“×”。判對得分,不判、判錯均不得分。)
1、施工圖預算的主要作用是,控制建設工程投資和主要物資需用量。 ( )
2、設計概算--施工圖預算--施工預算,組成我國現階段建筑工程預算體系。( )
3、室內、外樓梯均按房屋自然層計算建筑面積。 ( )
4、設計采用的砼強度等級或石子最大粒徑與定額不同時,均應作換算。 ( )
5、框架磚墻不分內、外墻,其長度均按凈長計算,其高度均按凈高計算。 ( )
6、現搗板與框架結構連接時,板按主梁和柱間梁內側的凈距計算;這類板套
用有梁板或平板定額。 ( )
7、對于磚柱,柱基和柱身的工程量合并計算,套用磚柱定額。 ( )
8、現搗屋面板有坡度時,仍套用板相應定額,基價不作調整。 ( )
9、單位工程綜合腳手架工程量等于單位工程建筑面積。 ( )
10、雨蓬、沿溝等抹灰,如局部鑲貼塊料時,按相應“零星項目”計算差價。( )
二、單項選擇題:(每小題1分,共10分。在每小題備選答案中選出一個正確答案,并將正確答案的代碼填在題中括號內。選對得分,不選、選錯均不得分。)
1、省94預算定額采取定額與基價合編的形式,基價部分實行全省統一基價,按本。 )有關規定進行調整。
A、造價管理 B、合同管理 C、靜態管理 D、動態管理
2、定額中遇有兩個或兩個以上系數時
2003 budget estimate pipeline construction project in Zhejiang Province Qualification Examination
"Construction Budget" mock examination paper (open book)
First, determine questions: (Paper 1 min, a total of 10 points. The right to play in the brackets "√", the wrong fight "×". Sentence on the scores, not sub, not the wrong sub-scores.)
1 Construction Budget's primary role is to control capital projects and major amount of material needed. ()
2, the design budget - Construction Budget - construction budget, construction budget for the system composed of the present stage. ()
3, indoor and outdoor stairs Junan housing construction area of natural floor basis. ()
4, designed with the concrete strength grade or size and scale is not the largest stones at the same time, should be converted. ()
5, regardless of the framework walls, the exterior wall, the length of the Junan net long basis, the calculation of its high Junan clear height. ()
6, trace and plate and frame structure are connected, the board by the main beams and columns inside the clear distance between the beam calculation; such board sets
With a slab or flat fixed. ()
7, for the brick columns, plinths and columns is engineering quantity together, apply the brick columns fixed. ()
8, there are trace roof slope when it is appropriate to apply the fixed plate, base price is not adjusted. ()
9, unit construction scaffolding construction is equal to unit integrated project construction area. ()
10, Awning, plaster along the trench, such as local Xiangtie block material, press the corresponding "piecemeal projects" Calculation of the difference. ()
Second, single-choice: (Paper 1 min, a total of 10 points. Meixiao Ti alternative answers selected in a correct answer and correct answer code fill in the title in brackets. Picked the score, not to choose not the wrong score.)
1, 94 provincial budget, a fixed and a fixed base price in the form of edited, base price part of the province to implement uniform base price, by province () with the relevant provisions to be adjusted.
A, cost management B, contract management C, static management of D, dynamic management
2, fixed in the event of two or more coefficients
