裝飾工程成品保護方案.doc
進入下載頁
成品保護方案
1.玻璃幕墻、鋁合金窗成品保護
1.1 幕墻、窗框四周嵌防水密封膠時,操作應仔細,不得污染幕墻、窗框。
1.2 拆搭腳手架、跳板其材料對鋁框要有相應的保護措施,否則不許在門窗框上拖拽,安裝管線,設備應防止撞壞幕墻。
1.3 不許在幕墻、窗框上撞擊,釘釘或刻畫,幕墻、窗玻璃安裝后立即貼上“小心玻璃”標志。
2.電信通訊成品保護
面板、模塊、配線架、機柜、控制箱、控制柜、攝像頭和報警器的安裝在內裝基本完成后進行。其他安裝與相關工序配合進行。
3.木門成品保護
3.1 木門扇、框及貼臉線和筒子板等進人場地后,必須將材料放置在通風良好,防雨防潮的地方并設專人管理。
3.2 油漆和膠等一些易燃材料必須放置在遠離火種和易燃產品處,并設專用房間加以保管。
3.3 產品在油漆和安裝完后,將產品用塑料布將油漆好的產品全部遮蓋起來,以免其他雜質對本產品的污染。
3.4 嚴禁撞擊門框扇及貼臉。
4.地面、墻面成品保護
4.1 地面抹好后,進行灑水養護7d內不得進行下一道工序操作。
4.2 運輸通道處的地面,養護完畢后鋪設保護層保護地面。
4.3 做好的地面,不允許有污染物落灑在地面上如:機油、油漆、油污、膠或粘
Product protection program
1. Glass curtain wall, aluminum windows product protection
1.1 curtain wall, window frame around the embedded waterproof sealant, the operation should be careful not to pollute the walls, window frames.
1.2 dismantling scaffolding, a springboard for its material on the aluminum frame should have the appropriate protection measures, or not allowed to drag on the door window frame, install pipes and equipment should be prevented from crashing wall.
1.3 allowed in the walls, window frames on the impact, nails or characterization, curtain wall, windows installed immediately after the moniker of "glass with care" signs.
2. Telecommunication product protection
Panel, module, patch panels, cabinets, control boxes, control box, camera and alarm devices installed in the interior after the basic completion. Installation and associated with other processes carried out.
3. Wooden product protection
3.1 wood door, frame and cheek lines and the cheese board into the site, the materials must be placed in well-ventilated, rain and moisture management where the designated persons.
3.2 paint and plastic and some other flammable material must be placed in the fire and flammable products away from the office and set up special rooms to be kept.
3.3 products in the paint and the installation finished, the product will be painted with plastic sheeting to cover up all the good products, so as to avoid other impurities contamination of the product.
3.4 non-impact door fan and cheek.
4. Floor, wall protection product
4.1 the ground after a good wiping, for sprinkler maintenance 7d shall not operate the next phase of the process.
4.2 Ground Transportation Corridor Agency, conservation protection after laying the ground layer of protection.
4.3 the ground do not allow for contaminants spilled on the ground down such as: oil, paint, oil, glue or sticky