海洋資料檔案異地儲藏館裝飾工程投標施工組織設計.doc
進入下載頁
施工組織設計
本施工組織設計之編制依據如下:
1. 發包方發出的本工程《招標文件》及相關附件、圖紙及補充文件
2.《工程測量規范》(GB50026-93)
3.《巖土工程李術規范》(GB29-20-2000)
4.《木結構工程質量驗收規范》(GB50206-2002)
5.《砌體工程施工質量驗收規范》(GB50203-2002)
6.《混凝土結構工程施工質量驗收規范》(GB50204-2002)
7.《鋼結構工程施工質量驗收規范》(GB50205-2002)
8.《建筑地面工程施工質量驗收規范》(GB50209-2002)
9.《建筑裝修工程施工質量驗收規范》(GB50210-2001)
10.《建筑給排水及采暖工程施工質量驗收規范》(GB50242-2002)
11.《建筑電器安裝工程施工質量驗收規范》(GB50303-2002)
12.《通風與空調工程施工質量驗收規范》(GB50243-2002)
13.《鋼筋焊接及驗收規范》(JGJ18-96)
14.《建筑工程施工質量驗收統一標準》((GB50300-2001)
第一章工程概況及施工范圍
第一節 工程概況
Construction Design
The preparation of the construction organization design basis are as follows:
1. Contractee issue of this project, "tender documents" and related accessories, drawings and additional documents
2. "Engineering survey" (GB50026-93)
3. "Geotechnical Engineering Li Shu norms" (GB29-20-2000)
4. "Wood construction quality acceptance" (GB50206-2002)
5. "Masonry Construction Quality Acceptance" (GB50203-2002)
6. "Concrete Construction Quality Acceptance" (GB50204-2002)
7. "Steel Construction Quality Acceptance" (GB50205-2002)
8. "Ground Engineering Construction Quality Acceptance" (GB50209-2002)
9. "Building renovation acceptance of construction quality" (GB50210-2001)
10. "Building water and Heating Engineering Quality Acceptance" (GB50242-2002)
11. "Building electrical installation acceptance of construction quality" (GB50303-2002)
12. "Ventilation and Air Conditioning Engineering Construction Quality Acceptance" (GB50243-2002)
13. "Steel welding and acceptance" (JGJ18-96)
14. "Construction Quality Check by" ((GB50300-2001)
Chapter Overview and construction of the scope of works
Section Project Profiles