隧道注漿加固工程施工組織設(shè)計(jì)方案.doc
進(jìn)入下載頁資料簡(jiǎn)介
北京大學(xué)站進(jìn)線電力溝工程位于北京市海淀區(qū)成府路中段,東起鐵路東側(cè)家具店,西至東升鄉(xiāng)鄉(xiāng)政府路口,全長(zhǎng)約500米。本工程電力溝為2.00×2.05m暗挖隧道。初襯200mm,二襯200mm,初襯和二襯之間為SBC120聚乙烯丙綸復(fù)合防水卷材。
Peking University Station into the ditch line of power engineering in the middle of Beijing Chengfu Road, east of the east railway furniture store, west junction Dongsheng township government, total length 500 meters. This project is 2.00 × 2.05m Power ditch excavated tunnel. Lining 200mm, the second lining 200mm, lining between the lining and two for the SBC120 polyethylene polypropylene fiber composite waterproofing membrane.
下載地址